Flooring

Manual Handling

CSR Hebel recommends using a trolley or other mechanical apparatus to move the panels around the work site. Manual handling, where people physically move a panel, should be kept to a minimum, with the weight being supported by an individual kept as small as possible. Any concerns regarding the weight to be handled should be discussed with the panel installing contractor.

To minimise the possibility of manual handling injuries, CSR Hebel suggests the following:

■ Use mechanical aids, such as trolleys, fork lifts, cranes and levers, or team lifting to move panels.
■ Keep the work place clean to reduce the risk of slips, trips and falls which can cause injury.
■ Plan these quence of installation to minimise panel movements and avoid awkward lifts.
■ Keep the panels dry.
■ Train employees in good lifting techniques to minimise the risk of injury.

Hebel products are cement-based, which may irritate the skin, resulting in itching and occasionally a red rash. The wearing of gloves and suitable clothing to reduce abrasion and irritation of the skin is recommended when handling Hebel products.

Architectural Specification

This specification should be adopted as a guide only, and shall be superseded by the contract specifications of the project. * Insert or select appropriate specifications.

Scope

The contractor shall furnish all material and equipment required to satisfactorily complete the installation and jointing of Hebel PowerFloor where indicated in the contract specification.

Materials

All AAC material shall be a Hebel PowerFloor panel as manufactured by CSR Hebel.

All accompanying fixings shall be those supplied by CSR Hebel or approved by the project engineer.

All lining materials shall be Gyprock plasterboard as manufactured and supplied by CSR Gyprock (or products of equivalent or better performance). All plasterboard shall be manufactured to meet the dimensional requirements of AS/NZS2588 ‘Gypsum Plasterboard’.

Steel frame components shall be those manufactured by Rondo Building Services Pty Ltd (or products of equivalent or better performance).

Construction adhesive shall be Fuller Max Bond as manufactured and supplied by Fuller (or products of equivalent or better performance).

All sealants shall be a polyurethane type with required fire and acoustic ratings, (or products of equivalent or better performance).

All infill materials shall be products manufactured and supplied by CSR Bradford® (or products of equivalent or better performance).

PowerFloor System

The contractor shall supply and install a Hebel PowerFloor system *PF-.........(...), in accordance with CSR Hebel Detached Houses & Low Rise Multi- Residential Floor Design Guide, NoHBLA185, and CSR Gyprock Fibre Cement Fire & Acoustic Design Guide ('The Red BookTM'), NoGYP500, and shall satisfy the following performance criteria.

The Hebel PowerFloor system shall have a Fire Resistance Level of *FRL.../.../... for a fire source ‘from above’ in accordance with the requirements of AS1530.4. Design of the joists shall allow for temperature effects.

Installation shall be carried out to the level specified for a field acoustic performance of *Dntw............ using cavity infill of *Bradford ............... (or products of equivalent or better performance).

Levels of Finish - Floor Covering

Prior to installation of the floor covering, the contractor shall ensure the installed panels are within the tolerances of the project specifications.The contractor shall ensure that all control joints are installed as per project specifications, panel joints are completely filled with Hebel Adhesive, minor chipping damage of the panels shall be patched with Hebel Mortar, and all sealants are installed as per manufacturer’s specifications.

Floor coverings shall be installed as per manufacturer’s specifications, unless specified otherwise in the contract documentation.

Ceiling System

The contractor shall supply and install the Gyprock Ceiling System *N°CSR......... in accordance with CSR Gyprock Fibre Cement Fire & Acoustic Design Guide ('The Red BookTM'), NoGYP500. The ceiling framing shall be lined with *......... layers of......... mm Gyprock......... plasterboard.

Levels of Finish - Ceiling  Systems

All ceiling framing systems, plasterboard lining, jointing and finishing shall be carried out to *Level ......... Level of Finish, in accordance with CSR Gyprock Plasterboard Residential Installation Guide, NoGYP547, AS/NZS2589.1 ‘Gypsum Linings in Residential and Light Commercial Construction - Application and Finishing’.

Plasterboard

The Hebel PowerFloor system ceiling framing shall be lined with *............ layer/s of ............mm Gyprock .................. plasterboard.

Plasterboard fixing

All layers shall be fixed to the framing (ie., timber or steel floor joists and/or steel furring channels) as specified for the relevant system in the CSR Gyprock Ceiling Systems Installation Guide, NoGYP570, other relevant CSR Gyprock technical literature, and Rondo Building Services Pty Ltd literature or steel frame manufacturer’s literature.

Jointing & Finishing

Jointing and finishing of the outer layer of plasterboard shall be in accordance with the CSR Gyprock Plasterboard Residential Installation Guide, NoGYP547.

Caulking

Where caulking is indicated in fire rated systems *........................ fire rated polyurethane sealant or fire rated backing rod with *.................. acoustic rated polyurethane sealant shall be used, and installed in accordance with the manufacturer’s recommendations.

Where caulking is indicated in wet areas, a *........................ polyurethane sealant must be used when caulking *non-fire rated/fire rated wet areas, as indicated, and installed in accordance with the manufacturer’s recommendations.

Important

Any variation or substitution of materials or assembly requirements, or compromise in assembly may result in failure under critical conditions.

Construction Details

Helbel Products

Helbel Products

Helbel Products

Helbel Products

Helbel Products

Helbel Products

Helbel ProductsHelbel Products

Helbel Products

Helbel Products

Helbel Products

Helbel Products

Helbel Products

NOTE:    • Fitted flooring is required where the bearing stress in the Hebel PowerFloor panel, at the top of joists or the top of blocking between joists exceeds 1MPa.

• The detailing of the cladding system shown below is for indicative purposes only. The project designer shall specify the construction details for the project.

hebel flooring

NOTE:    • For hold-down connections other than bolts, ensure the minimum requirements for embedment into timber is maintained. Refer to AS1684.2 for hold-down connection requirements.

• The detailing of the cladding system shown below is for indicative purposes only.The project designer shall specify the construction details for the project.

Hebel Products

Penetrations & Notching Details

Hebel Products

Wet Area Detail

Hebel Products

Balcony & Staircase Details

Heebel Products

Heebel Products